The Telstra Clayton data centre will be constructed as a new build on a brown field site to be constructed in 1816 – 1832 Dandenong Road, Clayton, Victoria 3168, Australia. The facility is required to be operational continuously all year round and shall be designed as a Mission Critical Facility.
The system distribution arrangement must be designed to be concurrently maintainable without impacting the operation of the IT data centre equipment.
The new data centre will be located in an existing Telstra site that also accommodates engineering and operations facilities as well as an existing data centre.
The NEC will have its own dedicated 11kV standby generators that will only have the capacity to cater for a maximum load of 10MVA. The Carpark Data Centre will have its own dedicated Diesel Rotary Uninterrupted Power Supply (DRUPS) system, Static UPSs and separate standby generator plant (SGP).
The Data Centre will be supplied via six (6) dedicated 22kV feeders that emanate from the NEC.
This specification includes for the installation, termination, and testing of this associated cabling including differential protection cabling between the two facilities.