Rockingham Hospital Phase 1

Client: Esslemont Building & Civil
June 29, 2015

Rockingham Hospital Phase 1

Client: Esslemont Building & Civil
June 29, 2015
Phase 1 of the Rockingham Hospital redevelopment posed a number of unique challenges for the Nilsen team.

Disconnection & removal of the existing Western Power HV supply and 2 x 500kVa transformers involved a 14hour shutdown leaving the entire hospital running on a sole backup generator, while 2 x new 1MVa transformers and new HV supply were installed into Substation No. 1.

Disconnection and removal of the existing MSB1 and the rerouting of all existing imperial MIMS submains to a new MSB1 also incorporated its own set of difficulties.

Both major shutdowns were completed ahead of schedule with the disruption of the working hospital kept to a minimum.

Download the factsheet here

Explore more case studies

Visy Glass Project Apollo (Yatala)

Visy Glass Project Apollo (Yatala)

The Visy Glass Recycling and Manufacturing Facility at Stapylton, Queensland, is a major industrial development combining a glass recycling cullet plant, container glass manufacturing facility, and finished goods warehouse on a greenfield and brownfield site. The...

read more

Get in touch

We’re here to deliver electrical technology solutions.

From large-scale infrastructure to tailored electrical solutions, reach out to our team today to find out how we can support your project.